Technology
An operating problem, solved.
Rochester is a mining operator, not a technology company. The recovery process came from working on a specific problem at Mina Real: manganese in the mineralized material.
- 01 · Problem
Manganese interferes with recovery.
Mina Real’s mineralized material carries a naturally high manganese content. Manganese occludes silver and interferes with conventional cyanide leaching, which historically limited recovery.
Illustrative only, not to scale. Proportions reflect the historical baseline (~43%) and industrial pilot results (62% mine mineralized material, 56% tailings). How the pretreatment works is not shown. - 02 · Research
A laboratory testing program.
In 2024, a laboratory testing program evaluated mine mineralized material, tailings, and blends of both.
- 03 · Solution
Pretreat, then leach.
The program identified a pretreatment combining ammonia bisulfite and sulphuric acid, applied ahead of conventional cyanidation. The pretreatment adds a step in front of the leaching process; it does not replace it.
- Tailings500 tpd design · plannedMineralized material160 tpd design
- New stagePretreatmentAmmonia bisulfite + sulphuric acid
- Conventional cyanidation↺ Water + cyanide recovered for reuse
- RecoverySilver & goldFiltered tailingsDry-stacked
- 04 · Validation
Lab first. Then a three-month industrial pilot.
Laboratory results were positive, with substantial improvements in recoveries. A follow-up three-month industrial pilot at the plant confirmed the lab work.
Silver recovery at the plant
Historical baseline, industrial pilot and reported fiscal-year results
Fiscal-year figures are reported plant results from the MD&A for the year ended May 31, 2026. Gold recovery was 99.60% in fiscal 2026 (fiscal 2025: 96.76%). Pilot figures are from a three-month industrial pilot.
- 05 · Implementation
A full-scale circuit.
A conceptual engineering study defined a full-scale circuit. Engineering, permitting, procurement and construction followed, with plant modifications beginning in October 2024, and the new circuit commenced operations on March 21, 2025.
Design capacity500 tpdTailings, tons per dayDesign capacity of the full-scale circuitDesign capacity160 tpdFresh mineralized material, tons per dayDesign capacity of the full-scale circuitEstimate~US$4MEstimated capital costConceptual engineering study estimate - 06 · Result
Improved recoveries.
The results have been positive, with improvements in both silver and gold recoveries. Improved cash flow followed, also aided in large part by improvement in commodity prices. A larger pretreatment tank is being added to increase capacity through the mill.
Historical~43%Historical silver recovery baselineExpectedOct 2026Larger pretreatment tank: expected completionMid to late October 2026. Expected to allow increased capacity through the mill